Parliamentary committee gives Egenco 2 weeks to fix gensets
Officials from the Parliamentary Committee on Natural Resources, Energy and Mining have given up two two weeks Energy Generation Company (Egenco), the company established to generate power, to fix broken power electricity generators.
The committee chairperson Welani Chilenga said it was surprising to note that six out of the 10 generators were not working yet utility supplier Electricity Supply Corporation of Malawi (Escom) was paying K1 billion every month in rentals for the generators.
This was observed when committee members visited the Egenco power station at Mapanga in Blantyre.
Egenco spokesperson Moses Gwaza said the generators came without backup spare parts.
He said Egenco would fix the generators which are down within the two weeks.
This is theft, how come you continue paying for something that’s not working? Where is Aggreko on this? I thought its their responsibility to repair them? And EGENCO is just watching and paying?This is why it was said by concerned citizens that this generator project is a scam, it started with the missing of fuel