LWSP Sets K20 Billion for Lilongwe City Sewer Rehabilitation & Expansion

Issues of poor sanitation and sewerage inefficiencies in Lilongwe City are expected to be a thing of the past as the poor and vulnerable households stand to benefit from improved and increased access to safely managed sanitation services once the Lilongwe Water and Sanitation Project (LWSP) is completed, an official has said.

Lilongwe Water Board (LWB) and Lilongwe City Council (LCC) are jointly implementing a 5-year World Bank/IDA funded project whose main objective is to increase access to improved water services and safely managed sanitation in Lilongwe City. LWSP which commenced in 2018 is expected to be completed by 30th June 2023.

Speaking to journalists on Monday during a media tour to the project sites across the city, LWB spokesperson, Maurice Nkawihe said the project has an allocation of US$25,000,000 (about K20 billion) for the sanitation component which will focus on sanitation improvements within the city.

“Under this component we are rehabilitating and expanding the sewerage network by upgrading existing sewer connections and installation of new connections. Poor and vulnerable households will be specifically targeted for support to improve their sanitation facilities. About 250,000 people stand to benefit from these sanitation interventions,” said Nkawihe.

Among others, the project is expected to have 5,000 new households connected to sewer lines; rehabilitate and upgrade the existing Kauma wastewater treatment plant, and support the construction of 8,000 improved sanitation facilities for households from low-income areas. The sanitation improvements will also cover 10 markets and 10 schools.

Meanwhile, sewerage network expansion works are underway in Area 1 (Falls), Area 49 Sectors 1 and 2 (Old and New Gulliver) and Area 47 Sector 4. Once completed, the households in these Areas will be connected to the sewer lines.

“The current stage (Phase 1) will connect new 3,096 households to the sewer system. The project is already in the process of identifying contractors for the construction of 1,000 household toilets,” Nkawihe added.

He said apart from rehabilitating and expanding the sewerage network, the project will also conduct sanitation marketing campaigns to encourage connection to sewer system and construction and use of improved toilets.

LWSP’s financing includes a US$75 million credit from World Bank/IDA, US$25 million grant from World Bank/IDA and US$2 million from the Government of Malawi.

Follow and Subscribe Nyasa TV :

Sharing is caring!

Follow us in Twitter
1 Comment
newest
oldest most voted
Inline Feedbacks
View all comments
SES
SES
2 years ago

Good sanitation project which long overdue in most areas.
Hope funds shall not be abused as we experience in other sectors of the nation.

Read previous post:
CDEDI blames fuel supply saga on infighting among Tonse Alliance partners

The Centre for Democracy and Economic Development Initiatives (CDEDI) has alleged that the ongoing fuel supply saga is a result...

Close